Mining & Construction

African Mining Generator Sets & Heavy Trucks

Diesel Purification

Key outcomes

Case Study

Stage 1 · Customer Problem

📋 Customer Problem

An international engineering contractor operating large-scale mining projects in Africa faced severe fuel quality issues threatening both power generation and heavy haul operations:

🛢️

Extremely Poor Fuel Quality

Locally supplied diesel had severe particulate contamination (ISO 24/22/19), causing frequent blockage and wear of precision HPCR injector nozzles.

💰

High Maintenance & Logistics Costs

Engine filter cartridges frequently blocked and required replacement. In remote Africa, spare parts logistics costs are extremely high, with delivery times of weeks.

Unplanned Power Outages

Generator set failures due to fuel system issues caused power outages across the entire mining area, resulting in significant production losses.

📉

Shortened Equipment Life

Impurities and trace free water in diesel accelerated fuel tank corrosion and engine wear, shortening equipment service life.

Stage 2 · Fuel Analysis · NEW

🔬 Fuel Analysis

Fuel sampling from the mining area's main storage tank revealed contamination levels far exceeding engine manufacturer specifications:

MetricBefore TreatmentAfter TreatmentImprovement
ISO 4406 Cleanliness~24/22/1912/9/66-7 levels ↑
Free Water (ppm)~250≤5080% ↓
Visual AppearanceDark, opaque with visible particlesClear, bright
Particle CompositionDust, mineral particles, wear metals≥99% removed at ≥3 μm99% ↓
TAN (mgKOH/g)0.200.0670% ↓

Values are representative based on African mining site conditions (remote supply chain, minimal pre-treatment, harsh storage environment). The dramatic improvement to ISO 12/9/6 exceeds typical engine manufacturer requirements (ISO 18/16/13).

Stage 3 · Solution

🛠️ Solution & System Configuration

The customer procured multiple sets of Jingyuan 12m³/h diesel filtration equipment, deployed at the mining area's main storage tank and fueling island front end:

Flow Rate
12 m³/h per unit
Membrane
Polymer Rigid Composite, 3 μm nominal
β Value
≥200 at rated pore size
Deployment
Main storage tank + fueling island front end
Water Removal
Oleophilic-hydrophobic synergistic separation
Regeneration
Gas-pulse regeneration (brief 5-15 min safety pause)
Function
Pre-fuel-entry particulate + water removal
Monitoring
Differential pressure monitoring

Key design decisions: The 3 μm nominal precision was selected to protect HPCR systems with 2-5 μm injector clearances. Multiple units were deployed in parallel to provide redundancy and ensure continuous fuel supply even during maintenance. The system was positioned at the fueling island front end to provide final-stage protection immediately before fuel enters equipment.

Stage 4 · Results

📈 Quantified Results

12/9/6
ISO Cleanliness Achieved
80%
Water Reduction
~70%
Injector Failure Reduction
0
Consumable Cost
MetricBeforeAfterImprovement
ISO 4406 Cleanliness~24/22/1912/9/66-7 levels ↑
Injector Nozzle FailuresFrequent blockage and wearSignificantly decreased~70% ↓
Filter Cartridge ReplacementFrequent, high logistics cost0 (3-year membrane life)100% eliminated
Unplanned Generator DowntimeMultiple incidents per monthNear-zero~90% ↓
Spare Parts Logistics CostVery high (remote Africa)Significantly reduced

By deploying this batch of filtration systems, the mining area's diesel quality was dramatically improved. Maintenance data shows a noticeable decrease in the unplanned replacement rate of engine injector nozzles. The fuel cartridge replacement cycle for generator sets has been effectively extended, reducing consumables procurement and logistics costs. Stable power supply ensured continuous mining operations.

Stage 5 · Lessons Learned · NEW

💡 Lessons Learned

Key Success Factor

The 3 μm nominal membrane precision was the critical decision for protecting HPCR systems with 2-5 μm injector clearances. Unlike nominal-rated cartridges that allow particle passage, the absolute pore geometry ensures zero unloading — captured particles cannot re-release under pressure spikes, which is essential in mining applications with frequent flow rate changes.

⚠️

Common Pitfall

Mining operations in remote locations often accept poor local fuel quality as "unavoidable" and compensate with frequent filter changes. In Africa, this approach fails because spare parts logistics can take weeks. Each filter change also introduces contamination risk during the maintenance process. Membrane filtration with gas-pulse regeneration eliminates both the consumable dependency and the maintenance contamination risk.

🔄

Replication Advice

Directly applicable to all African and remote-region mining operations with poor local fuel supply. The 12m³/h configuration suits typical mining site fuel consumption. For large operations with multiple mining areas, deploy one unit per fueling island plus one at the main storage tank. The zero-consumable design is especially valuable where logistics chains are long and unreliable.

"

Customer feedback

In the harsh environment of African mining, fuel quality is an important variable affecting availability rates. Jingyuan's filtration equipment effectively improved diesel quality. Our generator sets' reliability has been significantly improved, and we have saved considerable spare parts logistics costs.

Related cases

Mining & Construction

Get a technical solution

WhatsApp